Timeline for the CZMU coastal conservation investment programmes
2020

Coastal Risk Assessment and Management Programme
Additional shoreline protection engineering works at Holetown.
Advanced topographic mapping and oceanographic assessment studies.
Natural hazard risk analysis and assessment.
Update of the ICZM Plan, Act and draft regulations.
Institutional capacity development.
Completion of engineering designs for future shoreline protection works.
Advanced topographic mapping and oceanographic assessment studies.
Natural hazard risk analysis and assessment.
Update of the ICZM Plan, Act and draft regulations.
Institutional capacity development.
Completion of engineering designs for future shoreline protection works.
2012
2009
2000
1998
1996
1995

Feasibility and Pre-Investment Coastal Conservation Study
Shoreline protection pilot projects (Paynes Bay, Reads Bay, Accra).
Completion of the ICZM Plan for the south and west coasts.
Drafting of the Coastal Zone Management and Marine Pollution Control acts.
Establishment of the CZMU as a permanent agency of the GoB.
Completion of the ICZM Plan for the south and west coasts.
Drafting of the Coastal Zone Management and Marine Pollution Control acts.
Establishment of the CZMU as a permanent agency of the GoB.
1991
1984
1983